Case Study

Surrey County Council – Ashford Park Primary School

Client description

Ashford Park Primary School – Boiler replacement

Contract details

Replacement of all boiler plant, heating systems, hot & cold pipework, controls, etc to 5 individual plant rooms across a large primary school site.

The works were undertaken during term time and holidays on an occupied site, including evenings, nights & weekends; over a 14 month period.

Value

Circa £400,000 – £600,000

Duration

2017 / 2018