Client description
Brighton Hill Community School – Salix Lighting Upgrades
Contract details
A point-for-point LED lighting replacement of all internal fittings in a large Secondary School by utilising the SALIX funding scheme.
The replacement totalled approximately 1100 fittings. The project included the use of high level access equipment which was required to the sports hall, theatre and dining room.
This upgrade project ran through the summer holiday period and all of the light fittings were successfully changed to LED throughout the whole school.
Value
£181,000
Duration
July 2019 – September 2019